- ²ÝÁñÉçÇø Bond Progress
- December 14, 2020 Report to Board
-
In a presentation to the Board of Education on December 14, 2020, Chief Operations Officer Clete Welch provided an update to the Board.
Boswell High School
- Press box pad is being prepped.
- Dirt work between the turf room and offices are being graded.
- Plumbing is being installed for the freshman locker room.
- Walkway has been poured from the main building to the new athletic facility.
- Slab for the varsity and JVlocker room has been poured. CMU block has been delivered for wall construction.
- Slab preparations for the gymnastics offices and dressing rooms.
- Additional shortage and restroom for gymnastics area. The first row of CMU block has been laid.
- Turf room grade beam is being formed up. This is located next to the Max Newcom Gym.
Lake Country Elementary School
- Lift is being used to lift the joist to be installed in the cafeteria.
- East drive is being poured.
- Pump truck being utilized to assist in concrete pour on eastern edge of the property.
- Form boards have been staked in place and rebar is tied together for concrete pour.
- Retaining wall for detention pond is in the process of being formed up for concrete.
- Retaining wall is 90 percent complete.
- Decking has been installed above the joist in the cafeteria.
- Elevator walls are 90 percent complete.
- IFC walls are being installed in kindergarten and first grade hallway.
- CMU blocks are being installed in the kitchen area.
- Welder is installing beams between the cafeteria and gym.
- CMU block is being installed in the freezer area of the kitchen.
Maintenance Facility
- New view of the building from the road.
- Warehouse exterior metal panels are being installed.
Progress Update of Other Projects
- Security Upgrades at Multiple campuses and Jim Knight Maintenance facility Additions and Renovations - Prep work has been completed. Hardware will be delivered during the break. Install will also begin during the break.
- Central Office - Naming the general contractor is an action item for Board consideration at tonight’s meeting.
- Eagle Mountain HS – Design and site development continues.
- Wayside MS – Working on site development.