- ²ÝÁñÉçÇø Bond Progress
- June 15, 2020, Report to the Board
-
District New Construction Progress
In a presentation to the Board of Education on June 15, 2020, Chief Operations Officer Clete Welch shared updates about the following projects:
Copper Creek Elementary
- The front entrance is nearing completion
- The front building signage has been installed
- Hat channel is being installed to recieve acoustical panel
- Concrete is being prepped for flooring in the main lobby
- Classrooms are ready to receive furniture
Boswell High School
- Utilies are being completed
- The entrance is being expanded
- Old baseball fence has been removed
- Masonry for the ag science building is in progress
- Framing and ductwork is in progress
- Turf building rennovation is in progress
- Plumbing lines have been installed
- Demolition is in progress at the stadium
- New electrical building and pathway complete
- The parking lot, stormwater and asphalt removal is in place
Turf Projects
- projects in progress at Creekview MS, Highland MS, Prairie Vista MS, Willkie MS, CTHS, and SHS
Lake Country ES
- Propery has been mowed
- plat is progressing through city planning
Other Projects Progress
- Security upgrades - Construction Manager at Risk under consideration tonight
- Network Operations Center 0 Completion date August 2020
- Tennis Court Resurfacing - Saginaw HS, Prairie Vista MS, Ed WIllkie MS, purchase order has been created and coordinating schedule with Hellas Construction
- Tennis Wind Slats - Waiting for delivery at Saginaw HS, Prairie Vista MS, Ed Willkie MS, and CTHS
- Central Office - Site visit to pin the building corners down
- Eagle Mountain HS - Site visit with the architect and civil engineer
- Track Resurfacing - All work complete at BHS, CTHS, SHS
- Flooring Projects - Carpet and VCT complete at Chisholm Ride ES, Comanche Spring ES, Greenfield ES, and SHS; VCT and carpet complete at Prairie Vista MS; VCT replacement begins at Dozier ES